29/10/2026
⚙️ Pumping Station Automation Reconstruction | Part 3 — Final Commissioning
Bringing the entire system back online! 🚀
After replacing the damaged hardware and rebuilding the PLC programs, we completed the integration of the pumping station automation system.
✅ Reprogramming both Siemens S7-200 pump controllers.
✅ Reprogramming the master Siemens S7-300 CPU.
✅ Configuring and adjusting PROFIBUS communication between the controllers.
✅ Restoring synchronization between both pumps and the master control system.
✅ Integrating the OP277 HMI for system operation and monitoring.
✅ Final checks and commissioning of the reconstructed automation system.
💡 The result: A fully reconstructed control architecture, restored communication, and a pumping station ready for operational validation.
No original backups. Damaged hardware. A complete automation reconstruction.
This is industrial automation troubleshooting, PLC engineering, and commissioning in the field. 🛠️
OP277 PumpingStation IndustrialAutomation PLCProgramming Commissioning KCAutomationEngineering