10/15/2026
Project Spotlight - Cleveland WTP's - Residual Systems Improvements
North Bay Construction has completed the installation of the interior components of GST #4. The dome was set on 10/9/26. Platform, stairs & electrical installation is in the works.
BWC #2. Demo of the existing grout floor is on going. Fiberglass troughs are being rebuilt and new grout floor to be poured by 10/23/26. New 61’ dome is due to arrive by 10/23/26, Installation will follow.