Today this 18hp Greyhound leaves the shop to go back to the customer for them to finish the restoration.
People ask all the time about the timeline of these projects, so here is a snap shot
March 2025 received the engine .
June 2025 steel was ordered for the boiler .
September 2025 steel was received and construction started.
October 2025 boiler was halfway done
December 2025 boiler was complete
May or 2026 engine was all remounted on new boiler and ready to go home
Today 6/3/2026 the engine leaves CES to head back to the customer