The West Shore Lake Pontchartrain project is located in southeast Louisiana on the east-bank of the Mississippi River in St. The West Shore Lake Pontchartrain Chief’s report was published in June 2016 and the project received $760 million in funding in the Bipartisan Budget Act of 2018. The West Shore Lake Ponchartrain project features an 18.5 mile risk reduction system, comprising 13.2 miles of l

evees, 8 flood walls, 7 drainage structures, 3 gates, and 2 pump stations. Recent efforts build on previous construction accomplishments, including nine land-bridge access roads connecting existing state highways and I-10 to the future levee alignment, two sand placement contracts, pile load testing contracts, three stockpile contracts for sand and clay, and multiple mitigation bank awards.

Just a reminder, today is the final day posts will be made to the West Shore Lake Pontchartrain page. Beginning...
01/30/2026

Just a reminder, today is the final day posts will be made to the West Shore Lake Pontchartrain page. Beginning Feb. 1, 2026, this page will be archived and no longer active, and all future posts related to the West Shore Lake Pontchartrain project will be made on the main US Army Corps of Engineers, New Orleans District page. Please follow us there for any future updates.

01/26/2026

ICYMI: We’re continuing to answer your top questions about construction on the West Shore Lake Pontchartrain Project.

In this episode, Charlotte Clarke, Project Manager with the Lake Pontchartrain and Vicinity Branch, and Rene Poche, Public Affairs Specialist with the New Orleans District, share an update on the St. James Parish portion of the project.

01/14/2026

Join us as we answer your top questions related to the construction of the West Shore Lake Pontchartrain project. In this episode Kaitlyn Johnson, Project Manager in the Lake Pontchartrain and Vicinity Branch, and Rene Poche, Public Affairs Specialist, at the New Orleans District, break down what you need to know about the levee elevations included in the WSLP system.

Beginning Feb. 1, 2026, this page will be archived and no longer active. Please follow the main US Army Corps of Enginee...
01/13/2026

Beginning Feb. 1, 2026, this page will be archived and no longer active. Please follow the main US Army Corps of Engineers, New Orleans District page for all future updates regarding the West Shore Lake Pontchartrain project.

01/08/2026

West Shore Lake Pontchartrain contract 102 update.

Work continues to advance across multiple areas of the West Shore Lake Pontchartrain project at Contract 102. Crews are ...
01/08/2026

Work continues to advance across multiple areas of the West Shore Lake Pontchartrain project at Contract 102. Crews are splicing H-piles beneath I-10, which are steel beams driven deep to provide a strong foundation in soft soils, and surveying concrete piles at the North Montz Canal. In addition, construction of the Montz Canal Drainage Structure continues to progress, with concrete recently poured to form the base slab of the T-wall monolith which serves as the structural backbone of the drainage structure.

Clay is being hauled to Elevation 11 feet in non-hold sections, while vertical wick drains continue to be installed near Little Montz and at the tie in to contract 103 to stabilize the ground for long-term performance.

Stay tuned as steady progress is being made as we build safer, stronger infrastructure for the region.

12/10/2025

As 2025 draws to a close, let’s take a moment to reflect on the tremendous progress made on the West Shore Lake Pontchartrain Project. With each milestone, we're one step closer to enhancing the resilience of our communities. Stay tuned as we continue to make strides in delivering this critical infrastructure!

12/03/2025
Big strides are being made on the far western end of the project at Contract 114A at Hope Canal! We’ve completed clearin...
12/03/2025

Big strides are being made on the far western end of the project at Contract 114A at Hope Canal! We’ve completed clearing and grubbing, and construction on the levee is moving full speed ahead. The embankment has reached its final elevation of +8.5’

Additionally, the contractor has installed the 96” culvert at Hope Canal. The pre-load area is also underway, having reached elevation 9’, with a target hold period elevation of 20’.

Exciting progress as we continue to lay the foundation for a stronger, more resilient future. Stay tuned for more updates as we continue to push forward!

Embankment placement at West Shore Lake Pontchartrain contract 109 is moving along, with the tie-in to Contract 108 near...
11/25/2025

Embankment placement at West Shore Lake Pontchartrain contract 109 is moving along, with the tie-in to Contract 108 nearly complete. West and east pre-load areas have reached elevation 17’ and are now under a hold period. The west levee is at elevation 4.5’, and the east levee has reached its final elevation of 8.6’. Geotechnical instrumentation at the West Preload site is complete, ensuring a strong, stable foundation for the next phases of the project. Stay tuned as we continue building safer, stronger infrastructure for the future!

11/21/2025

West Shore Lake Pontchartrain contract 106 update.

Address

7400 Leake Avenue
New Orleans, LA
70118

Opening Hours

Monday 6am - 6pm
Tuesday 6am - 6pm
Wednesday 6am - 6pm
Thursday 6am - 6pm
Friday 6am - 6pm

Telephone

+15048622545

Alerts

Be the first to know and let us send you an email when West Shore Lake Pontchartrain - New Orleans, USACE posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to West Shore Lake Pontchartrain - New Orleans, USACE:

Share