Recently 10K Engineering finished a design build project featuring a UR robot to automate a process and reduce labor for...
02/13/2026

Recently 10K Engineering finished a design build project featuring a UR robot to automate a process and reduce labor for Fort Recovery Industries, Inc.
Challenges
1) Cycle time (6 second target)
2) This was attempted before WITHOUT success
3) Quality control, failed parts passed on

Outcome
We worked this project in phases to test each assumption and manage early investment.

Phase 1: Simulate the cycle, is 6 seconds even realistic. Realized we would need a dual EOAT.

Phase 2: Build simplistic system and prove out the cycle time with real parts. Had to modify the process which was previously done by hand

Phase 3: Final build, re-use as many components from Phase 2.

RESULT:
- 5 second cycle time
- Reduced operator count from 8-12 down to 4-6
- Consistent quality

Do you need to improve quality and reduce operators? Let’s talk about it.

đŸ’¯ Shoutout to Allied Automation Inc. for their support

Address

537 S. Broadway Street, STE 204
Greenville, OH
45331

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Telephone

(937) 216-1828

Alerts

Be the first to know and let us send you an email when Craig Sink posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share