10/01/2025
Please enjoy our full field construction progress video of our steel project for Trader Joe's out in beautiful Palmdale, CA.
This project consisted of 4 different buildings, an 850,000 sq. ft. warehouse hub, a 250,000 sq. ft. freezer building, a 7,000 sq. ft. accessory building, and a 1,000 sq. ft. pump house building. Our customers, Fisher Construction Group and KPRS Construction, needed an extremely tight turnaround on fabrication and er****on of all of this steel for their client, Trader Joe's. In effort to help, we erected steel without the tilt walls in place to allow us to make more time for progress out of a tight schedule for the team. United Steel performed and proved that their request was not as impossible as many had thought.
Huge thanks to our team: Sang Detailing, Brown Strauss Steel, Canam Steel Corp., Next Level Steel, and last but definitely not least, Precision Steel Erectors. You all allow us to pull off the "impossible". 🙏