06/15/2026
đźš§ Cape Coral Yacht Basin | Project Update #4
Progress continues at the Cape Coral Yacht Basin, with sheet pile installation for the boat ramp and cofferdam now complete. Crews are preparing to begin sheet pile installation along the south basin wall as work advances toward the day docks.
Over the next two weeks, crews will drive sheet piles along the south basin wall, install a dewatering system for the boat ramp and box culvert, and begin pouring the concrete seawall cap.
Follow along on our Ongoing Projects page:
https://www.wcgfl.com/ongoing-projects