06/03/2026
Fyi Leganesnon
๐๏ธ๐ ๐๐ฅ๐๐ ๐ณ, ๐ฎ๐ฌ๐ฎ๐ฒ, ๐ฆ๐๐ง๐จ๐ฅ๐๐๐ฌ
๐ ๐ฒ:๐ฌ๐ฌ ๐.๐ . ๐ง๐ข ๐ฒ:๐ฌ๐ฌ ๐ฃ.๐ . (๐ญ๐ฎ ๐ต๐ผ๐๐ฟ๐)
๐ง REASON: To conduct annual preventive maintenance of Sta. Barbara & Leganes Substations.
๐ AFFECTED AREAS:
๐. ๐ช๐๐ข๐๐ ๐ ๐จ๐ก๐๐๐๐ฃ๐๐๐๐ง๐ฌ ๐ข๐ ๐๐๐๐๐ก๐๐ฆ
๐. ๐ช๐๐ข๐๐ ๐ ๐จ๐ก๐๐๐๐ฃ๐๐๐๐ง๐ฌ ๐ข๐ ๐ฆ๐ง๐. ๐๐๐ฅ๐๐๐ฅ๐, ๐๐ซ๐๐๐ฃ๐ง:
1. CABUGAO NORTE
2. JIBAO-AN
3. BALABAG
๐. ๐ฃ๐ข๐ฅ๐ง๐๐ข๐ก ๐ข๐ ๐ฃ๐๐ฉ๐๐:
1. AMPARO
2. MALI-AO
3. PAL-AGON
4. PORTION OF CABUGAO SUR (along Vice President Fernando Lopez Avenue)
We humbly ask for your understanding on this scheduled power interruption.
โ ๏ธ Power may be restored earlier than or as scheduled, so please consider all lines and equipment energized.
๐๐ฐ: ๐๐ฌ๐ข๐, ๐๐ฌ๐๐ , ๐๐ฌ๐ฅ๐, ๐๐ฌ๐๐ฆ
๐๐๐
. ๐๐.: PR2026-3-7-056