09/09/2026
πŸ—οΈ KLGCC | SITE PROGRESS UPDATEπŸ’ͺ Concrete slab works completed, with bar bending & beam reinforcement works progressing ...
09/09/2026

πŸ—οΈ KLGCC | SITE PROGRESS UPDATE
πŸ’ͺ Concrete slab works completed, with bar bending & beam reinforcement works progressing on site.

πŸ“ˆ Concrete Slab – COMPLETED βœ…
🚧 Next: Beam reinforcement & timber beam installation. **KGSB, Moving Forward!**

πŸ—οΈ KOLAM 2 | ISTANA NEGARAπŸ’ͺ Geobag installation & sand filling works progressing at Slope B & C.πŸ“ˆ Slope C – 90% | Slope ...
09/09/2026

πŸ—οΈ KOLAM 2 | ISTANA NEGARA

πŸ’ͺ Geobag installation & sand filling works progressing at Slope B & C.

πŸ“ˆ Slope C – 90% | Slope B (2m) – 90%
🚧 Steady progress on site β€” KGSB, Moving Forward!

πŸ—οΈ KANDANG KUDA | ISTANA πŸ’ͺ Work in progress β€” Horizontal Drain, Cascade Drain & Culvert works ongoing.πŸ“ˆ Cascade Drain | ...
09/09/2026

πŸ—οΈ KANDANG KUDA | ISTANA

πŸ’ͺ Work in progress β€” Horizontal Drain, Cascade Drain & Culvert works ongoing.

πŸ“ˆ Cascade Drain | U-Drain Paddock
β˜” Despite the afternoon rain, works continued as planned.

KGSB β€” Progressing Together!

πŸ—οΈ PROJECT PROGRESS UPDATEKLGCCπŸ“… 28 August 2026KGSB continues to carry out site works at KLGCC, focusing on ground compa...
01/09/2026

πŸ—οΈ PROJECT PROGRESS UPDATE

KLGCC
πŸ“… 28 August 2026

KGSB continues to carry out site works at KLGCC, focusing on ground compaction and drain hacking works, alongside ongoing gabion installation.

πŸ“Š Current Progress:
β€’ Gabion cage installation – 7 layers
β€’ Drain hacking – Ongoing
β€’ Ground compaction – Ongoing

Material deliveries including gabion stone, BRC A10 and corrugated pipes were received on site.

Works are progressing with the next phase focused on continued ground compaction and hacking works.

KGSB β€” Building Progress, Delivering Excellence.

πŸ—οΈ PROJECT PROGRESS UPDATEIstana Negara | Kandang KudaπŸ“… 29 August 2026KGSB continues to progress with site works at Kand...
01/09/2026

πŸ—οΈ PROJECT PROGRESS UPDATE

Istana Negara | Kandang Kuda
πŸ“… 29 August 2026

KGSB continues to progress with site works at Kandang Kuda, focusing on cascade drain works, HD drilling, formwork installation and site preparation.

πŸ“Š Current Progress:
β€’ Cascade Drain – 55%
β€’ Sump – 25%
β€’ 450mm U-Drain – 100%
β€’ Horizontal Drain works – Ongoing

Works are progressing as planned, with horizontal drain works scheduled for the next phase.

KGSB β€” Building Progress, Delivering Excellence.

πŸ—οΈ PROJECT PROGRESS UPDATEIstana Negara | Kolam 2KGSB continues to make steady progress on site, with ongoing works incl...
01/09/2026

πŸ—οΈ PROJECT PROGRESS UPDATE
Istana Negara | Kolam 2

KGSB continues to make steady progress on site, with ongoing works including geobag installation, slope cutting and pipe installation.

πŸ“Š Current Progress:
Slope C – 90% completed

Works are progressing as planned, with excavation and geobag installation scheduled for the next phase.

KGSB β€” Building Progress, Delivering Excellence.

Address

9-3, Jalan PJU 8/5A, Damansara Perdana
Petaling Jaya
47820

Opening Hours

Monday 08:00 - 17:00
Tuesday 08:00 - 17:00
Wednesday 08:00 - 17:00
Thursday 08:00 - 17:00
Friday 08:00 - 17:00

Alerts

Be the first to know and let us send you an email when Kreatif Geoteknik Sdn Bhd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Kreatif Geoteknik Sdn Bhd:

Shortcuts

Share