28/08/2026
Successful Factory Acceptance Test (FAT) of 3 x 300kVA Cummins Canopy Gensets – JPPS Project
We are pleased to share the successful completion story of the Factory Acceptance Test (FAT) for three (3) units of 300kVA Cummins Canopy Diesel Generator Sets designated for the Jabatan Perkhidmatan Pembetungan Sabah (JPPS) project.
The FAT was conducted in the presence of representatives from JPPS and the project team in our Inanam workshop to verify that all generator sets complied with the specified technical requirements and performance standards. The test was carried out in accordance with the relevant JKR specifications and inspection requirements, including visual inspection, operational checks, engine protection verification, and load bank testing.
During the FAT, each generator set undergone a comprehensive series of tests to confirm:
* Compliance with approved technical submissions and project specifications.
* Proper operation of engine and alternator systems.
* Functionality of control and monitoring systems.
* Verification of engine protective devices and safety interlocks.
* Stable voltage and frequency performance under transient load and overloading conditions.
* Successful load acceptance and response during simulated operating scenarios.
The test demonstrated that all three Cummins gensets performed satisfactorily, meeting the required operational parameters and quality standards. The successful FAT provides confidence that the equipment is ready for delivery, installation, and commissioning at the project site.
This achievement reflects the strong collaboration between the manufacturer, project team, JPPS representatives, and all stakeholders involved. Early verification through FAT ensures that any potential issues are identified and resolved before site deployment, resulting in smoother installation and reduced commissioning risks.
We would like to extend our appreciation to the JPPS team, contractors, and all personnel who participated in the FAT process. Their commitment and cooperation contributed significantly to the successful outcome of this important project milestone.
Another successful step forward towards delivering a reliable power solution for JPPS. ✔️🔋⚡