18/08/2020
Assembly of Bottom panel block
Bottom Panel Block Assembly
Sequence and Procedure
1) Attached the sealing tape to the fl**ge for all of the bottom panel.
2) Method to Apply Tapes
a) The sealing tape should be applied to all assembled fl**ge surfaces.
b) The centre side of the sealing tape should be overlapped by about 50mm (as shown in the below photo )
3) To assemble a bottom panel block, fIrst connect several bottom panels into a sub-block. Determine the block size according to the site condition, the work space, number of workers, use or non-use of a crane, etc.
A block that is too large cause difficulty in relocation and other work. Therefore, it is recommended that one block be limited to 10 panels x 2rows.
4) Arrangement and type of bottom panels.
Place bottom panels one by one upside (as shown in Fig. 2).
When installing a drain nozzle, place a pit panel in the pre-determined position.
5) Assembly of Drain Panel
Using a hole saw(for a small bore),and a jigsaw(for large bore), the required holes may be cut into panels.
6) Assembly of sub-blocks is done by connecting panels in one direction only.
7) All bolts/nuts for connecting bottom panels shall be M10 X 50 ℓ. As for 8 Bolts/nuts are used fo a 1m length side and 4 are used for 0.5m length side of a panel.
8) Perforate a hole using a fixture
9) For bolt / nut tightening sequence : First tighten the 3th bolt/nut from each end of the fl**ge. Then tighten 4th, 5th,6th, and 1st,8th. Lastly the 2nd, 7th bolts/nuts.
10) Adjusting by levering the tapered bars horozontally and vertically.
11) Assemble one more sub-block using the same procedure as above.
12) Connect together two assembled sub-blocks into one complete 10-panel bottom block.
DAEJOO ENG. CO.,LTD
Sky Seo (Managing Director)
Website : www.daejoosmc.com
Blog1 : grp-water-tank.blogspot.com
Blog2 : blog.naver.com/biotank420
E-mail : [email protected]
Managing Director's Mobile / Whatsapp : +82-10-2758-7147
General Manager's Mobile / Whatsapp : +82-10-7741-8555