27/03/2026
Kick-Off Meeting Successfully Held for Vientiane Airport Improvement Project
On 27 March 2026, the Kick-Off Meeting for The Project for Improvement of Vientiane Airport, a Japanese Grant Aid Project, was successfully held at the DCA Conference Room in Vientiane, Lao PDR.
Gyros Corporation is honored to serve as the Lead Consultant in a joint venture with Azusa Sekkei. The project is being implemented with Hazama Ando Corporation as the contractor, under the leadership of the Department of Civil Aviation (DCA).
The meeting was attended by key stakeholders, including the JICA Laos Office, DCA, Airports of Laos (AOL), L-JATS, LANS, and ATS, marking a strong start to collaboration on the project.
Project Overview:
This project officially commenced today and is scheduled for completion in April 2028. The scope includes:
• Expansion of the international departure lounge
• Installation of an arrival baggage claim belt in the domestic terminal
• Rehabilitation of apron and taxiway pavements
• Rehabilitation of the aeronautical ground lighting system
Gyros Corporation remains committed to contributing our expertise to enhance airport infrastructure and support the continued growth of aviation in Lao PDR.