3S Engineers

3S Engineers Greetings from 3S!!! Thanks!

We at 3S introduce ourselves as Economical and Sustainable solution provider for Steel Plants. 3S is a pool of Industry Expert, Professional & Experienced Personnel have experience in Furnace & CCM to provide best Service, Solution & Satisfactory Results We at 3S introduce ourselves as Economical and Sustainable Solution providers. 3S is a pool of Industry Experts, Professionals, and Experienced P

ersonnel having experience from Electrical & Mechanical, Furnace, CCM, FES, AOD, LRF, EOT Crane, Transformer Manufacturing Companies and reputed plants to provide the best Service, Solution, and Satisfactory Results for the Steel Plants. We are a Jalna, Pune & Ahmedabad-based team with vast experience setting up Steel Plants to achieve maximum production with optimum operating cost. We help in the perfect selection of Auxiliary Products, Erection Materials and Add-on Products to gain maximum efficiency of main machinery like Furnaces & Caster with a commitment to achieve the best Plant & Machinery performance. OUR BUSINESS VERTICALS
✅ Engineering Solutions
✅ Design, Manufacturing, and Supply of Auxiliary Products
✅ Erection and Commissioning
✅ Operation and Maintenance Contracting
✅ Plant Efficiency and Productivity Improvement
✅ Supply of Spares and Consumables
✅ Plant Automation

AREA OF EXPERTISE
1️⃣ Steel Melting Shop
2️⃣ Rolling Mill
3️⃣ Induction Melting Furnaces
4️⃣ Continuous Casting Machines
5️⃣ Refinery Furnaces: LRF, AOD, VD, etc.
6️⃣ Primary & Secondary Fume Extraction Systems (FES)
7️⃣ Substation & Electrical Systems
8️⃣ Water Complex: WTP, Pressure Sand Filter, Cooling Tower, etc.
9️⃣ Scrap Processing Yards: Shearing, Sorting & Bundling Machine
🔟 Auxiliary Products: FES, Ladle Cars, EOT & Stationary Cranes, Poking, Scrap Charging Devices and more.
1️⃣1️⃣ Specialised Applications: In-line Heater & TMT Epoxy Coating. Advantages with 3S:-
✔ Ex- Furnace, CCM, FES & Crane team’s extensive experience and support
✔ Industry experts offering the best solutions
✔ Proven track record of achieving performance goals
✔ Long-term association commitment
✔ Dedicated engineer support

You can reach us at [email protected] or by mobile number +91 7028345258 for more information and detailed discussion.

20/10/2025

Happy Diwali 🎇🪔🎉🎆

Happy New Year from 3S Engineers and Forzo Industrial Solutions!At 3S Engineers and Forzo Industrial Solutions, your tru...
01/01/2025

Happy New Year from 3S Engineers and Forzo Industrial Solutions!

At 3S Engineers and Forzo Industrial Solutions, your trust and collaboration inspire us to deliver excellence. As we step into 2025, we wish you a year filled with success, prosperity, and remarkable growth. May this year bring exciting opportunities and lasting achievements for you and your business.

Our Expertise
1.⁠ ⁠Engineering Solutions – Greenfield & Expansion Projects
2.⁠ ⁠Auxiliary Products – Design, Manufacturing & Supply
3.⁠ ⁠Plant Automation
4.⁠ ⁠Spare Parts & Consumables
5.⁠ ⁠Plant Efficiency & Productivity Improvements
6.⁠ ⁠Fabrication, Er****on & Commissioning Works
7.⁠ ⁠Operation & Maintenance Contracts
8.⁠ ⁠Revamping, Relocation & Re-Installation

We look forward to strengthening our partnership and driving success together in the year ahead.

Best regards,
Vikas Singh
3S Engineers & Forzo Industrial Solutions

As we celebrate our nation's Independence, 3S Engineers wishes everyone a day of pride, joy, and reflection. Happy Indep...
15/08/2024

As we celebrate our nation's Independence, 3S Engineers wishes everyone a day of pride, joy, and reflection. Happy Independence Day!

03/05/2022
Induction Melting Furnace Er****on & Commissioning work within 4 days of power shutdownDay 1Task 1 - Existing Furnace 1 ...
19/04/2022

Induction Melting Furnace Er****on & Commissioning work within 4 days of power shutdown

Day 1
Task 1 - Existing Furnace 1 dismantling - 5 to 6 Hrs.
Task 2 - Core cutting & new bolt civil grouting, Platform cutout & civil grouting of Furnace 1 - 26 Hrs.
Task 3 - Complete crucible ready outside - 2 days
Task 4 - Pipeline from pump house to crucible room with header & manifold - 2 days

Day 2 & 3
Task 1 - New crucible placement and interconnection of cables, bus-bar & hose pipes, etc. - 30 Hrs.
Task 2 - Existing capacitor rack dismantling & placement of new with height adjustment - 24 Hrs.
Task 3 - Hydraulic pipeline work - 5 to 6 Hrs.
Task 4 - Dismantling of Furnace 2 - 5 to 6 Hrs. (Shutdown started)
Task 5 - Core cutting & new bolt civil grouting, Platform cutout & civil grouting of Furnace 2 - 26 Hrs.
Task 6 - Platform fabrication work

Day 4
Task 1 - Water & Hydraulic Pipeline testing - 5 to 6 Hrs.
Task 2 - Bus bar connection with existing Power Supply Unit
Task 3 - Complete testing of Furnace 1
Task 4 - Silica lining of Furnace
Task 5 - Start-up of Furnace 1 (Shutdown completed)

Day 5
Task 1 - New crucible placement and interconnection of cables, bus-bar & hose pipes, etc. - 30 Hrs.
Task 2 - Complete testing of Furnace 2
Task 3 - Silica lining of Furnace
Task 4 - Start-up of Furnace 2

Hurdles:- Running plant, Space constraints, Extra civil work, Core cutting, Some short of er****on materials.

Conclusion:-
Planning & Ex*****on done within the given time frame.
Low impact on monthly production (only 4 days production loss).

****on

It does not matter how you are planning for the preventive maintenance of your machinery, but by doing it on a regular b...
28/03/2022

It does not matter how you are planning for the preventive maintenance of your machinery, but by doing it on a regular basis you definitely will get the benefits;

1. Longer life of the equipment or plant
2. Provide more organized, planned work environment
3. Proper inventory management
4. Reduced production downtime, resulting in fewer machine breakdowns
and many more benefits.

20/03/2022

A glimpse of an ongoing Er****on & Commissioning of Air Pollution Control System

****on

On the occasion of the festival of colors, I hope God fills your life with colors of joy, happiness and love. Happy Holi...
18/03/2022

On the occasion of the festival of colors, I hope God fills your life with colors of joy, happiness and love. Happy Holi !!!

Team Forzo

Address

705, 6 & 7, Park Plaza Business Center, Porwal Road, Dhanori
Pune
411047

Opening Hours

Monday 10am - 6pm
Tuesday 10am - 6pm
Wednesday 10am - 6pm
Thursday 10am - 6pm
Friday 10am - 6pm
Saturday 10am - 6pm

Alerts

Be the first to know and let us send you an email when 3S Engineers posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to 3S Engineers:

Share