01/06/2026
Week 08 Maidstone East Station, Kent.
Throughout all of Week 08 we worked closely with VolkerFitzpatrick Ltd and the Southern Renewals Enterprise to deliver a drainage scheme at Maidstone East Station during a blockade which provided 24/7 access to the line.
A challenging week for the team with just about every possible condition thrown in for good measure including some of the hottest weather ever recorded in May, excessive water flow that required contineous over pumping, below ground obstructions, and reduced digging rates due to CRT management.
The scope included;
• 252m of both 6ft and 10ft drainage through the Maidstone East Station and into the Week St Tunnel.
• Two drainage UTX's.
• Drainage outfall connection through the platform at a depth of 3m.
Works were supported by Engineering trains which required careful planning. Digging works were done with a bendy boom Liebherr A924 and a Doosan DX140 fitted with a Nox tiltrotator. Two further RRV's, each with two trailers and boxes were used for material distribution to and from the Engineering Trains. Great effort all round from everyone involved and thanks to our team, supply chain and client.