Metal-Framed Pontoon, Rye
This September, WMS built a metal-framed pontoon for a client in .
The frame was made in two halves and transported to site with the end HDPE floats already secured. The two frames were fixed together and the two central floats attached onsite.
As there was no shore access at the install location, we launched the pontoon further along the river and towed it into place. We moored the pontoon with four piles β to allow it to respond to changing water levels β then screwed in all the synthetic decking.
Weβll be returning in the next few weeks to install the custom gangway.
Our pontoons are custom built to suit your needs and location, so get in touch to see how we could meet your requirements. We look forward to hearing from you!