05/06/2026
Progress is continuing on our Slovenia office project 🇸🇮
The roof is almost finished, with only a few small details left. The façade is about halfway done and is starting to show the final look of the building.
Inside the building, work is moving forward on all floors. Electrical and mechanical systems are being installed, and drywall work is also ongoing everywhere.
Outside, the next step is the entrance fountain. It will be poured with concrete later this week.
More updates will follow as the project moves closer to completion. 🚧