23/09/2026
Project progress from our Fabrication team.
This 300NB mild steel pipework and structural steelwork is currently being delivered for a leaching plant at a Goldfields mine site.
The fabrication scope was expedited to meet the client’s project requirements, while still successfully passing all required quality assurance and inspection benchmarks.
With fabrication complete, the package is now on its way for rubber lining and painting before progressing to the next stage of the project.
Another strong effort from the team to maintain quality while working to a tight project schedule.