For those who are curious about how these homes get assembled on site, our process goes like this:
Step 1: our foundation gets layed off to match our panel diagram, so that we make sure our plans are matching up with reality.
Step 2: we secure our custom steel brackets to the panel and to the telehandler and crane. It is important that this is done properly as these panels can weight 1000 pounds and a slip is very dangerous
Step 3: apply silicone to the side of the previous panel and to the foundation. Air tightness and control is a big part of energy efficiency and moisture management, so proper detailing is imperative.
Step 4: lift the panel into place, ratchet it tightly to the previous panels and secure with nails and heavy duty screws.
Thats pretty much all there is to it, as most of the building of the walls happens in our warehouse!