11/06/2026
⚒️ Amey, on behalf of Transport Scotland, is undertaking essential resurfacing on the southbound M77 at Junction 2, including the Junction 2 on slip, from Monday 15th June until Wednesday 24th June 2026 between 9pm and 6am each night.
⚠️ This work will be delivered in three phases:
1️⃣ Phase One (Monday 15th June - Saturday 20th June) will require overnight closures of the southbound M77 between Junctions 2 and 3 and the Junction 2 on slip, with mainline traffic diverted via Barrhead Road, Kennishead Road and Nitshill Road to rejoin at Junction 3.
2️⃣ Phase Two (Saturday 20th June - Sunday 21st June) will operate under a contraflow with hard shoulder running on both carriageways between Junctions 1 and 3, with the Junction 2 northbound on slip also closed.
3️⃣ Phase Three (Sunday 21st June - Wednesday 24th June) will require overnight closures of the southbound M77 between Junctions 2 and 3 and the Junction 2 on slip, with diversions following the same route as Phase One.
Full details of this project can be found below ⤵️
🔗 https://swtrunkroads.scot/scottish-south-west-trunk-roads/a77m77/m77-junction-2-resurfacing/